Installation of Biogas Plant to Produce 65,000 m3/day of Biogas for Pak Ethanol (Pvt.) Ltd.

Industrial Alcohol

Noveltech International Inc. was awarded an EPC Turnkey contract for the Installation of a Biogas plant to produce 65,000 cubic meters per day of Biogas
Noveltech carried out the complete undertaking in house including the complete Engineering Design, Civil, Mechanical, Electrical and Instrumentation works. Commissioning of the plant was also carried out by Nordtec International.
The plant is in successful operation and has met or exceeded all its intended process parameters.

Contract Type

EPC Turnkey

Location

Matli, Badin

Client

Pak Ethanol (Pvt.) Ltd.